BREAKING NEWS: Crystal Pier demolition set

by Cole Dittmer
Friday, September 14, 2012

In an email to Wrightsville Beach planning and parks director Tony Wilson, Hans Lonander of Intercoastal Contracting said the company would begin work to remove the last three bays of the easternmost end of Crystal Pier on Tuesday, Sept. 18, at noon. Lonander said the project would be completed before dark that same day.  

Intercoastal Contracting will complete the work with a truck and fork loader on the beach, and boats in the water to pull away the section of the pier to be removed. Once removed from the pier, Lonander said the pieces would either be dragged to the beach to be towed away or taken to the company's barge depending on their condition. 

No impact from the demolition is expected for the remainder of Crystal Pier and the Oceanic restaurant plans on operating on a regular schedule. 

 Email this to a friend    Printable version